written 7.9 years ago by |
Hydrology & Water Resources Engineering - May 2014
Civil Engineering (Semester 5)
TOTAL MARKS:
TOTAL TIME: HOURS
1 (a) Explain the various methods of determining average rainfall over a catchment
due to storm. Discuss relative merits and demerits of each.(7 marks)
1 (b) Define unit hydrograph. Describe the procedure of deriving a unit hydrograph
from a given flood hydrograph.(7 marks)
2 (a) 1 Explain the following terms:
1. Precipitation.
2.Infiltration capacity.
3.Evapo-transpiration.
4.Infiltration Rate.
5.Hydrograph.
6.Floods
7.Drought.(7 marks)
2 (b) Describe in detail the factors affecting infiltration.(7 marks)
2 (c) A storm with 11cm precipitation produces a direct surface runoff of 6.2 cm.
The time distribution of the storm is given in the following table.
Time from start in hour | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Incremental rainfall in each hour in cm | 0.5 | 1.0 | 1.8 | 2.6 | 2.0 | 1.5 | 1.2 | 0.4 |
Compute the Φ index of the storm.(7 marks) 3 (a) Define runoff, sub-surface runoff and direct runoff. Explain the factors affecting runoff.(7 marks) 3 (b) The ordinates of flood hydrograph from a 4 hour rainfall are given below. Derive the ordinates of 4 hour unit hydrograph for a catchment area of 640 km<sup.2< sup=""> .
<colgroup span="12" style="text-align: center;" width="85"> </colgroup>
Time (hours) | 0 | 4 | 8 | 12 | 16 | 20 | 24 | 28 | 32 | 36 | 40 |
Discharge m3/s | 30 | 68 | 205 | 410 | 330 | 254 | 195 | 133 | 95 | 58 | 30 |
Define the following in relation to aquifer
3 (c) 1 Confined aquifer(1 marks) 3 (c) 2 Unconfined aquifer.(1 marks) 3 (c) 3 Aquiclude(1 marks) 3 (c) 4 Aquifuge(1 marks) 3 (c) 5 Transmissibility(1 marks) 3 (c) 6 Storage coefficient(1 marks) 3 (c) 7 Specific yield(1 marks) 3 (d) A 30 cm diameter well completely penetrates a confined aquifer of permeability 45 m/day. The length of strainers is 20 m. Under steady state of pumping, the drawdown at the well was found to be 3.0 m and radius of influence was 300 m. Calculate the discharge.(7 marks)
Write a short note on
4 (a) 1 Rational formula for flood estimation(4 marks) 4 (a) 2 Flood forecasting and warning(3 marks) 4 (b) Explain various causes of flood and their preventive measures.(7 marks) 4 (c) Explain the procedure to determine the reservoir capacity using mass curve.(7 marks)
Describe in brief
4 (d) 1 Reservoir sedimentation(4 marks) 4 (d) 2 Components of power house(3 marks)
Write a short note on
5 (a) 1 Causes of drought(4 marks) 5 (a) 2 Water conservation(3 marks) 5 (b) Explain various methods of water harvesting.(7 marks) 5 (c) Explain flood frequency analysis.(7 marks) 5 (d) Explain functional requirements of water resources projects.(7 marks)