written 7.8 years ago by | • modified 6.6 years ago |
(I) average busy hour traffic per subscriber. (2) Traffic capacity per BTS (3) required member of base stations per zone (4) The hexagonal cell radius for the zone. Subscriber usage per month = 150 minutes Days per month = 4 Busy hour per day = 06 Allocated spectrum = 4.8 MHz Frequency raise plan = 4/12 RF channel with = 200 KHZ (full rate) Present number of subscribers in the zone = 50,000 Subscriber growth = 5% per year Area of the zone = 5090 km2 Initial installation bused on a four year design capacity of a base station (transceiver) (BTS) = 30 Erlangs Traffic capacity of a GSM cell at 2% Gos (using Erlang B table = 8.2 Erlangs
Mumbai University > Electronics and Telecommunication > Sem8 > Wireless Networks
Marks: 10 M
Year: May 2016
Explain this in details : 1) RF carriers per cell with a reuse factor of 4 ...WHY ONLY 4 IS IT ASSUMPTION?? From where 24/4*3 =2 (3 cells per BTS) came?
2) TRAFFIC/BTS =8.2*3=24.6 ....WHERE 3 CAME FROM?