Step 1:-
Total length =.23∗3+6.23∗2+2.33∗2+3.23∗4+1.83+1.43+6.46∗3+5.23∗2+4.23=80.06m
No of junction = 12

Trapezoidal portionV=(A1+A22)∗H=(0.38∗0.38+1.2∗1.27∗0.42)=0.333m² Trapezoidal portionV=(A1+A22)∗H=(0.38∗0.48+1.2∗1.37∗0.52)=0.456m²
Rectangular portion=1.2∗1.27∗0.15=0.22m³VF1=0.333+0.22=0.553m³ Rectangular portion=1.2∗1.37∗0.15=0.246m³VF2=0.456+0.246=0.702m³
Step 2:-

Prepare an abstract sheet for above
Sr No |
Description |
Qty |
Unit |
Rate |
Unit of rate |
Amt |
1 |
Brickwork in superstructure of GF |
43.156 |
Cu.m |
3850 |
Per cum |
166150.6 |
2 |
20mm thick external plastering in CM(1:4) |
76.54 |
Sq.m |
15 |
Per sq.m |
1148.1 |
3 |
Excavation for foundation |
79.16 |
cum |
10 |
Per cum |
791.6 |
Total =168090.3