Work out the quantities of the following items from given plan & section

Work out the quantities of the following items from given plan & section

(a) Excavation for foundation

(b) Brickwork (CM= 1:6) in superstructure of ground floor

(c) Concrete (M20) in footing

(d) 20 mm thick External plastering in CM 1:4 upto terrace level

1 Answer
1
46views

enter image description here

Step 1:-

Total length =.233+6.232+2.332+3.234+1.83+1.43+6.463+5.232+4.23=80.06m

No of junction = 12

enter image description here

Trapezoidal portionV=(A1+A22)H=(0.380.38+1.21.270.42)=0.333m² Trapezoidal portionV=(A1+A22)H=(0.380.48+1.21.370.52)=0.456m²

Rectangular portion=1.21.270.15=0.22m³VF1=0.333+0.22=0.553m³ Rectangular portion=1.21.370.15=0.246m³VF2=0.456+0.246=0.702m³

Step 2:-

enter image description here

Prepare an abstract sheet for above

Sr No Description Qty Unit Rate Unit of rate Amt
1 Brickwork in superstructure of GF 43.156 Cu.m 3850 Per cum 166150.6
2 20mm thick external plastering in CM(1:4) 76.54 Sq.m 15 Per sq.m 1148.1
3 Excavation for foundation 79.16 cum 10 Per cum 791.6

Total =168090.3