In the blanking die-set design, the first step is to prepare blanking layout i.e. the position of the work pieces in the strip and their orientation with respect to each other. This is known as Scrap Strip Layout. Following are the factors which affects the strip or stock layout.
Material Thickness (mm) | B (mm) |
---|---|
0.8 | 0.8 |
0.8 to 3.2 | t |
Over 3.2 | 3.2 |
The feed or advance or the length of one piece of stock required to produce onblank is ,
f= W + b
The number of blanks which can be produced from one length of stock can be found as ,
Where , a = back scrap or front scrap
b= scrap bridge
h & w= Height and Width of the component.
F=feed or advance.
T=thickness of the material.
L= length of the sheet.
N= number of blanks to be produced.
Y=scrap remaining at the end of the length.