The following table given the activities of a project with the details. Draw resource histogram based on EST. If only 10 labours are available, then how will you schedule the activities?
written 8.3 years ago by | modified 2.8 years ago by |
Activities | 1-2 | 1-3 | 2-3 | 2-4 | 3-5 | 4-5 |
---|---|---|---|---|---|---|
Duration | 8 | 8 8 | 4 | 9 | 6 | |
Labour / Day | 4 | 6 | 5 | 3 | 6 | 5 |
Mumbai University > Civil Engineering > Sem 8 > Construction Management
Marks: 10M
Year: May 2015